The National Paediatric Hospital Development Board was appointed by the Minister in 2013 to design, build and equip the new children's hospital on a campus shared with St. James's Hospital in Dublin 8, a paediatric outpatient and urgent care centre at Connolly Hospital Blanchardstown and a paediatric outpatient and emergency care centre at Tallaght University Hospital. Both satellite centres were handed over to CHI in 2019 and 2021, respectively, and are now fully operational.
BAM was instructed to proceed with the phase B above-ground works on the new children's in January 2019. In February 2024, Government approved enhanced capital and budget sanctions, bringing the total approved capital budget to €1.88 billion for the NPHDB component of this important project. The revised Government-approved increase included provisions to address areas not originally included in the 2018 budget, a number of which were clearly set out in the independent review carried out by PWC in 2019. The PWC report, which noted that the children's hospital was unique in scope, scale and complexity, also noted the number of project risks that had the potential to place further cost pressures on the approved capital budget. These risks included contractor entitlements under the contract; the outturn of provisional sums, recovery of construction inflation above 4%, the need for additional capacity and capability in the executive team of the NPHDB, changes in healthcare policy and regulations, and the contractor's right to claim for additional true costs in line with public works contract provisions.
Project costs, like other areas of the construction sector and wider society, have been impacted by external pressures, including impacts to supply chains arising from the pandemic and other global events such as the war in Ukraine and Brexit. The NPHDB addressed all of these risks and previously unidentified costs in its engagement and discussions with stakeholders ahead of the approval of the capital increase and believes that the enhanced budget of €1.88 billion reflects the additional requirements at the appropriate level. As of the end of August 2024, the total amount spent on the project by the NPHDB was €1.478 billion, including VAT.
I turn to progress to date. As the committee can see from the images and information pack we provided, construction on the NCH is approaching its final stages. The main focus relates to bringing all the rooms and spaces within the hospital up to the completion standard required by the contract. In addition, the technical commissioning is being undertaken and will continue until substantial completion. This work stream is approximately 40% complete. The external works include the main entrances, road junctions, emergency department car park, upgrades to the St. James’s campus internal roads, hard and soft landscaping, gardens and play areas. The connecting paths to the St. James’s adult hospital are well advanced with outstanding elements such as the new CHI and St. James's ambulance yard and canopy programmed to be complete by quarter 4 of 2024. The specialist clinical equipment built into the hospital such as MRI, CT, X-ray, C-arms, AGVs, etc., are installed and are being commissioned.
In 2024, the NPHDB will complete its procurement of the medical and non-medical equipment to be installed post-substantial completion. Almost €66 million of clinical equipment has already been procured. The most advanced and contemporary equipment is being procured for the hospital. Where equipment is required to interface with the CHI's electronic healthcare record, that is being developed by CHI, and this has been delivered to CHI for validation and testing. The construction of the helipad is complete and test flights will take place towards the end of 2024 and continue into early 2025.
The NPHDB procured ClearSphere as its contractor to undertake four specialist fit-outs within the NCH comprising the pharmacy, the radio-pharmacy aseptic compounding units, the stem cell laboratory and the biosafety laboratory. These specialist fit outs commenced in September 2024 and are due for completion in quarter 1 of 2025.
In February 2024, construction of the new Ronald McDonald house commenced, which is located across from the main entrance of the new children’s hospital. Clancy Construction Limited was appointed to design and build this facility, which will provide accommodation for 52 families each night, more than double the accommodation available at the current Ronald McDonald house in Crumlin. The new facility is already 30% complete, on budget and due to complete in quarter 3 of 2025.
In the past four years, the main contractor, BAM, has shifted its substantial completion date 14 times. In the past 12 months alone, BAM has shifted the substantial completion date four times, pushing out the completion date by a total of eight months. BAM is currently communicating June 2025 as its anticipated substantial completion date. In the absence of a written, contractually compliant, realistic and resource-loaded programme, the NPHDB cannot and will not simply accept BAM’s ongoing deferral dates. The employer’s representative, which is the independent contractor administrator, has not accepted this latest update, and has requested that BAM submit a revised baseline programme, in accordance with the requirements in the contract. A baseline programme is a critical requirement, fundamental to any construction project, as it provides a clear approach and timeline for works under way up to substantial completion, allowing for work to happen in an efficient and effective manner. The absence of a baseline programme on any construction project, especially one of the scale of the new children’s hospital, is completely unacceptable. BAM’s continued failure to provide a compliant baseline programme, and its shifting of dates, is not acceptable to the NPHDB, nor to our colleagues in CHI. It shows a complete disregard for internationally recognised professional processes and contractual procedures. The approach being taken by BAM also shows complete disregard for the sick children and young people and their families, as well as the dedicated and excellent staff in Children’s Health Ireland. It is clear to the NPHDB that the biggest factors contributing to the continued delay to completion are BAM’s continued insistence on offering rooms and areas within the hospital as complete when they are still incomplete, BAM’s continued failure to manage the project execution and BAM’s continued unwillingness to resource the project appropriately. This is why BAM is consistently failing to deliver on its planned commitments month on month.
BAM’s most recent forecast completion date is June 2025. This is 31 months behind the current contractual completion date of November 2022 and four months later than the substantial completion date the NPHDB provided to the Committee of Public Accounts in May 2024. In the contract programme provided by BAM in January 2019, it committed to a peak resource of more than 1,700 productive operatives. The highest level of resources provided by BAM to date was in June 2022 with circa 1,260 productive operatives. In 2024, there has been an average of 774 productive operatives on site. This dropped to 612 in August 2024 and was 631 in the first two weeks of September, which is unacceptable.
BAM has failed to resource this project sufficiently. This is evidenced by their continued failure to meet their own planned progress, the low monthly valuations and the continual shifting of the completion date. Since September 2023, BAM has, on average, achieved 64% of its planned progress. As of today, not one room has been fully completed in line with the standard and finish set out in the contract. There are 5,678 clinical spaces in the new hospital and while, to date, BAM has offered 3,128 as complete, none were completed to the required standard. All rooms offered by BAM require additional work prior to our team being in a position to sign them off as complete. BAM persists in offering sections of the hospital for review and sign-off when they are very obviously incomplete. BAM is currently abdicating its contractual responsibilities with regard to its quality management plan, fit-out inspection plan and final room inspection plan. BAM contractually undertook to deliver a building that is completed to the standard expected and with all snags addressed. The State is paying for a high-standard building complete to the level designed and I assure the committee we will not accept anything less. In order to ensure that the handover process is appropriately managed and completed, the NPHDB has had to assign additional resources to this handover process, and we are holding BAM to account on its processes.
Given BAM’s reputation in the market as a tier 1 contractor, the NPHDB finds its continued failure and refusal to comply with its obligations under the contract to be completely unacceptable. The manner in which BAM has progressed the works towards substantial completion is, and has always been, completely unacceptable to the NPHDB. The outcome being a loss of benefit to the State and importantly to sick children and their families, due to the delay in substantial completion of Ireland’s new children’s hospital.
The NPHDB is continuing to do everything in its power to compel BAM to conclude its work and fulfil its contractual responsibilities. BAM is not fulfilling its contractual obligations and consequently, we have moved to withhold 15% of certified payments due to BAM. This is a lever available to the NPHDB within the contract and we have initiated it again. The NPHDB previously withheld 15% of moneys due to BAM between May 2020 and February 2021, when BAM’s programme was deemed by the ER to be non-compliant. The NPHDB also threatened to withhold 15% in 2023. This was not actioned as BAM did provide a baseline programme.
Meanwhile, BAM continues to submit large volumes of claims, including duplication and triplication of the claimed time and value. It is the view of the NPHDB that BAM is seeking to implement a strategy to exert pressure on the State to secure additional moneys above the contract sum, by whatever means. The NPHDB is robustly defending claims that it considers to be without merit or to be inflated to prevent cost escalation and to protect the public purse. Regardless of how many times BAM asks, BAM will not be given another cent beyond what it is entitled to under the contract.
Where there have been changes instructed by the NPHDB - and it is not unusual on a construction project of this nature that there would be some changes instructed by the employer - we pay BAM for additional resources, and their supervision to minimise the impact on the programme.
We continue to do everything in our power to compel BAM to conclude its work and to fulfil its contractual responsibilities, including notifying it of the NPHDB's intention to apply liquidated damages for late completion.
I very much regret to have to report today that BAM is continuing to fail in its contractual obligations. It is a source of frustration, concern and anger that we are dealing with the issues that have been set out. I assure the committee that the NPHDB has not left any stone unturned or any legal route unexplored in our efforts to seek to influence and, indeed, compel BAM to meet its contractual obligations, but to date the efforts have yielded limited return. The approach by BAM to this project is unacceptable and we continue to do all in our power to ensure the hospital is delivered to the standard required as soon as possible.